Construction work on the bridge over the Stolp Canal is currently on hold. We have been informed of this by the responsible regional road authority:
"There are two reasons for the quiet on the construction site: On the Woltersdorf side, a temporary injunction has been obtained because it is feared that the construction machinery being used could cause damage to the neighbouring houses. The court has not yet made a decision on this issue. Until this is done, the construction work cannot continue.
The construction of sheet piling was due to begin on the Rüdersdorf side. It has now emerged that the metal elements planned for construction are not available in the required dimensions. Material shortages are currently an issue in many industries, including ours. It is still unclear when construction work can continue. We regret this development because it delays the construction work on the transport link that is so important for both towns."